Flagship Projects

Port Rehabilitation

Port Rehabilitation

Tanzania Ports Authority (TPA) as an Implementing Agency of The Government of the United Republic of Tanzania, received a loan from the International Development Association (IDA) towards the cost of the Dares salaam Maritime Gateway Project (DMGP).

The DMGP has been developed as a multi-development partner initiative to improve the effectiveness and efficiency of the Port of Dar es Salaam. The following lists of components are included in the DMGP

  1. Deepening and strengthening of existing Berths 1 to 7 to 14.5 m below CD, and constructing a new multipurpose berth at Gerezani Creek;
  2. Deepening and widening the entrance channel and turning basin in the port to the end of Berth 11 to 15.5 m below CD;
  3. Improving the rail linkages and platform in the port;27 and
  4. Deepening and strengthening of existing Berths 8-11, to 14.5 m below CD.

Tansheq provided the services for conducting Environmental and Social Impact Assessment (ESIA) for rehabilitation of berth 8-11 to 14.5 m below CD. Specifically, ESIA objectives are to:

  • Ensure that environmental considerations are explicitly addressed and incorporated into the development decision making process
  • Anticipate and avoid, minimize, or offset the adverse significant biophysical, social and other relevant effects of development proposal
  • protect the productivity and capacity of natural systems and the ecological processes which maintain their functions
  • promote development that is sustainable and optimizes resources use and management opportunities
  • Promote the implementation of the Environmental Management Act, 2004 and all other laws and decision-making process related to the goals and objectives of this project.